PM prods Discos to restore power supply on war-footing in flood-hit areas
Companies restore supply from 46 out of 81 grid stations
Stay tuned with 24 News HD Android App
On the directions of Prime Minister Shehbaz Sharif, the administration is working on war-footing to restore electricity in flood-hit areas across the country, reported 24NewsHD TV channel on Saturday.
PM Shehbaz himself is monitoring the work of power restoration in areas hit by large-scale deluges and the authorities will report him about the progress on work on daily basis. All the high-ups in power division have been directed to accelerate efforts in this regard.
The distribution companies have so far restored power supply from 46 grid stations out of 81 grid stations.
On the directions of Premier Shehbaz, the contact numbers of Discos’ chief executives and information about power division website have been given in the newspapers.
In his tweet today, Prime Minister Shehbaz wrote: “A massive national effort is underway to restore essential services in the flood-hit areas. NHA, DISCOs, PTA & other federal departments have done amazing work against the heaviest of odds & largely rehabilitated the damaged infrastructure. My appreciation for all public servants.”
A massive national effort is underway to restore essential services in the flood-hit areas. NHA, DISCOs, PTA & other federal departments have done amazing work against the heaviest of odds & largely rehabiliated the damaged infrastructure. My appreciation for all public servants.
— Shehbaz Sharif (@CMShehbaz) September 3, 2022
According to details, initially, a total of 881 feeders of 11 KV power had been affected during the monsoon rains and floods affecting supply to about 975,000 consumers, however, 475 feeders had been restored, with power being supplied to 70600 consumers.
To avoid power electrocution incidents, work on 35 grid stations in the flood-affected areas had not commenced yet. These included; 25 grid stations in Balochistan, 5 in Sindh, 5 in Khyber Pakhtunkhwa.
Two transmission line of 220 KV of National Transmission and Dispatch Company had been affected from Sibi to Quetta and from Dadu to Khuzdar. The work on Dadu to Khuzdar transmission lines would be completed which would restore 300 MW power supply in the affected areas whereas the work on Dadu to Khuzdar would be completed by September 10. Flood water had damaged 10 towers in these areas.
The restoration work was also in progress from Sibi to Mach transmission line.
Two supply lines of Peshawar Electric Supply Company from Chakdarra to Barikot and from Swat to Matta would be restored till September 10 whereas Madyan power grid station would be restored with power supply from Daral Khwar power generation plant.
In Sindh province, 5 grid stations and 2 grid stations in Balochistan had been still inundated under 3-4 feet of flood water and the power in these stations would be restored with the recession of flood water.
Reporter Awais Kiyani